Category archive: Featured Projects

Loganair Building, Glasgow Airport

Isolation of power, soft strip and demolition works. Start Date:  September 2015 Completion Date: October 2015 Client: Balfour Beatty

Mavor Avenue, East Kilbride

Asbestos removal, demolition works and crushing. Start Date:  September 2015 Completion Date: December 2015 Client: McTaggart Construction

Glasgow Airport Terminal Remodelling

Start Date: May 2015 Completion Date: February 2016 Client: Balfour Beatty

Stenhouse & SBS (Strathclyde Business School)

Start: 9th June 2014 Expected Completion:  August 2015 Completion Date:  July 2015 Client: Balfour Beatty Construction Internal strip out of all walls, partitions, ceilings and external features at both SBS and Stenhouse buildings.

Demolition of Black Cat Studios

Start: 27th April 2015 Completion Date:  21st July 2015 Client: McTaggart Construction Ltd

Demolition of Ruchill Kelvinside Church

Start 13th Oct 14 End 17th Oct 14 Client: Half Bridge Engineering Solutions

Demolition of former Social Work Offices

Start: 11 Aug 14 Completed: October 2014 Client: City Property (Glasgow) LLP

Phased Demolition of the Veterans Cottages at Erskine Hospital

Start: Oct 2013 Completed: Feb 2014 Client: Erskine Developments Ltd Works included the protection of trees and excavation and profiling in preparation for landscaping of the site.

Removal of Asbestos and Demolition of former Kayfoam Factory Paisley

Removal of Asbestos and the Demolition of former Kayfoam Factory on Neilston Road, Paisley. Commenced January 2013 Completed by end of October 2013 Client Aldi Stores.

Demolition of The Stuart Hotel East Kilbride

Demolition of The Stuart Hotel, East Kilbride Commenced February 2013 Completed by June 2013 Client: G1 Group PLC.4 Pictures taken by Colin Mearns,  Herald and Times Group.